The initial results of the ultimate-load test are positive. More extensive analysis and review are required before the test can be deemed a success.
"The test program has been more robust than any conducted on a Boeing commercial jetliner," said Scott Fancher, vice president and general manager of the 787 program, Boeing Commercial Airplanes. "It has taken countless hours of hard work by the Boeing team and our partners to work through the static test program. Everyone who has been involved in this effort over the past several years should be very proud of their contributions to ensuring the safety of the 787 Dreamliner.
"We are looking forward to the technical team's report on the details of the test results," said Fancher. It will take them several weeks to work through all of the data.
During each second of the more than two-hour test, thousands of data points were collected to monitor the performance of the wing. Key data points are monitored real-time during the test, but all of the data will be evaluated in the weeks ahead.
787 Dreamliner Background
The 787 Dreamliner is an all-new twinjet designed to meet the needs of airlines around the world in providing nonstop service between mid-size cities with new levels of efficiency. The airplane will bring improved levels of comfort to passengers with larger windows, bigger baggage bins and advances in the cabin environment, including lower cabin altitude, higher humidity and cleaner air. Delivery of the first 787 is planned for the fourth quarter of 2010.
Contact:
Lori Gunter
787 Communications
+1 206-931-5919
Photo and caption are available here: http://boeing.mediaroom.com
SOURCE Boeing
Contact: |
Boeing
Lori Gunter, 787 Communications Phone: +1-206-931-5919 Web: http://www.boeing.com |