Jubilee Line Remains Operational while London Underground Replace Tunnels Lining (Bentley Systems)

 EXTON, Pa., U.S.A. – Dec.22, 2015 – Bentley Systems, Incorporated, Following public criticism for passenger disruption caused by long-term engineering programs, this project was a first for London Underground Limited (LUL) as it replaced the tunnel lining over a 215-meter section of the Jubilee Line, while it remained fully operational.

With working times in the tunnel limited to 2.5 hours per night, it was essential that LUL build a cohesive team and leverage its collective intelligence. Deployed via ProjectWise, the common data environment (CDE) and workflows defined within British Standard 1192 ensured a single source of truth for all project data, and helped LUL effectively execute the project.

London Underground Limited
London Underground Limited

Bond Street to Baker Street Tunnel Remediation Project
  Bond Street to Baker Street Tunnel Remediation Project 

With the use of Bentley technology for 3D visualization and animation, 4D planning, 3D printing, and virtual reality, all stakeholders and decision makers understood the design and project intent without ambiguity. LUL realised these advantages on the project:

  • A complete 3D laser scanned model of the site and infrastructure enabled the creation of a 3D model, eliminating the need for additional site inspections and surveys.
  • Time savings of up to 15-20 percent were realized by starting many design and assurance processes earlier in the project lifecycle, which resulted in creation of a highly coordinated design solution and project plan early in the project timeline.
  • Design reviews, 4D scheduling, and other steps taken to evaluate constructability compressed timelines. For example, by commissioning two segment handling plants (SHPs) the team was able to reline the tunnel from both ends, which doubled productivity and resulted in completing the project four months earlier than originally scheduled.

Garry Pratt, project manager, Bond Street to Baker Street Tunnel Remediation Project, concluded that “Bentley Systems solutions helped LUL build a cohesive, collaborative design, assurance, and construction delivery team, allowing us to leverage the collective intelligence of the group. Their software ensured that we were able to manage uncertainties inherent in today's complex infrastructure projects, and deliver with confidence.”



Contact:

 

Bentley Systems, Incorporated
Press Contact:
Christine Byrne, +1 203-805-0432
Email: Email Contact |  
Follow us on Twitter: @BentleySystems

Featured Video
Editorial
More Editorial  
Jobs
Design Verification Engineer for Blockwork IT at Milpitas, California
Sr. Silicon Design Engineer for AMD at Santa Clara, California
GPU Design Verification Engineer for AMD at Santa Clara, California
Senior Firmware Architect - Server Manageability for Nvidia at Santa Clara, California
Senior Platform Software Engineer, AI Server - GPU for Nvidia at Santa Clara, California
CAD Engineer for Nvidia at Santa Clara, California
Upcoming Events
MEMS & Sensors Executive Congress (MSEC 2024) at Château-Bromont Hotel in Bromont Quebec Canada - Oct 7 - 9, 2024
PCB West 2024 at Santa Clara Convention Center Santa Clara CA - Oct 8 - 11, 2024
DVcon Europe 2024 at Holiday Inn Munich City Center, Munich Germany - Oct 15 - 16, 2024
International Test Conference (ITC) at United States - Nov 3 - 8, 2024



© 2024 Internet Business Systems, Inc.
670 Aberdeen Way, Milpitas, CA 95035
+1 (408) 882-6554 — Contact Us, or visit our other sites:
AECCafe - Architectural Design and Engineering TechJobsCafe - Technical Jobs and Resumes GISCafe - Geographical Information Services  MCADCafe - Mechanical Design and Engineering ShareCG - Share Computer Graphic (CG) Animation, 3D Art and 3D Models
  Privacy PolicyAdvertise